The enhanced volatilization of the soil was estimated to cost $1,916,000 over a nine month period, but without construction or maintenance costs thereafter (EPA 1988).
The combination method suggested for groundwater treatment would cost $3,916,000 in total with an eleven year implementation period, and would include a $905,000 construction cost and $390,000 in annual maintenance (EPA 1988).
Remedial Design/Remedial Action
![]() |
| Reich Farm Groundwater Plume |
1995 ESD/Construction Completion/Cleanup Completion
In 1995 an Explanation of Significant Differences was created to allow for public commentary on the changes to the RD/RA (EPA 1998). The ESD indicated that the new plan would save the project $2 million by negating the need to create a well for treatment and by utilizing the treated water for municipal uses rather than re-injecting the water back into the groundwater supply (EPA 1998). No changes were ever suggested for the treatment of the contaminated soils at Reich Farm and soil remediation was completed by May of 1995, although the volume of contaminated soils was more than seven times larger than originally estimated (EPA 1998).
The groundwater treatment system completed construction in 1997 and by 1998 a Preliminary Close-Out Report had already been submitted (EPA 1998). Four activated carbon units were added to the treatment system in 1997 as a measure to remove compounds that had been more recently identified (EPA 2003). In June of 1999 an additional containment well was constructed in order to further protect unimpacted wells in the Parkway well field (EPA 2003). This was because one year earlier in 1998, another Explanation of Significant Differences was released that indicated that two of six wells within the Parkway well field that had been being used for groundwater treatment were determined to still have low levels of contamination (EPA 1998). The ESD included a recommendation from the NJDEP that these two wells be excluded from use as public water supply unless it became absolutely necessary down the road (EPA 1998). These same contaminants have later been linked to a high incidence of childhood cancer among residents whom received drinking water from the Parkway well fields (UCC 2003).
Reich Farm Future Site Use
![]() |
| SAN Trimer |
The EPA issued the last five year review in 2008 and did not recommend any further cleanup procedures, but established continued sampling requirements for the site due to concerns over a new breed of semi-volatiles known as “SAN Trimer” that had developed due to reactions within the treatment wells (EPA 2008). The EPA continues to perform studies that are testing the relative toxicity of SAN Trimer and attempting to determine its potential as a carcinogen (EPA 2008).
Conclusions About Superfund
The Superfund process ultimately works because it can help answer the question of “who is going to pay for the cleanup?” and this is often the most important question when dealing with contaminated sites. The biggest problem under the current system, in my opinion, is the lack of funding given to it by the government and that would be my main tweak. The Environmental Protection Agency currently relies on the finding of PRPs (potentially responsible parties) in order to charge them with the cleanup because the “Superfund” has essentially been empty for years now.
Often times it becomes difficult to find PRPs at a site or things get tied up in litigation, meanwhile sites continue to degrade and pollution and contaminants continue to remain in an environment longer than they should have to. If the Superfund was restored to where it had been previously the EPA would be able to begin cleanup at sites such as this and then go after potentially responsible parties to seek reimbursement, rather than to seek initial funding of cleanup. This would help make the process more successful in the future when dealing with Superfund contamination sites.